File Name: | C:\Program Files (x86)\BLCC5\projects\FEMPEnergy.xml |
---|---|
Date of Study: | Wed Dec 20 07:01:30 CST 2017 |
Project Name: | Heating/Cooling System |
Project Location: | District of Columbia |
Analysis Type: | FEMP Analysis, Energy Project |
Analyst: | Courtney Mayer |
Comment | Replacement of Baseboard/ AC System with Heat Pump in Park Service House |
Base Date: | April 1, 2017 |
Service Date: | April 1, 2017 |
Study Period: | 15 years 0 months(April 1, 2017 through March 31, 2032) |
Discount Rate: | 3% |
Discounting Convention: | End-of-Year |
Base Case | Alternative | Savings from Alternative | |
---|---|---|---|
Initial Investment Costs: | |||
Capital Requirements as of Base Date | $1,500 | $3,000 | -$1,500 |
Future Costs: | |||
Energy Consumption Costs | $15,654 | $10,697 | $4,957 |
Energy Demand Charges | $0 | $0 | $0 |
Energy Utility Rebates | $0 | $0 | $0 |
Water Costs | $0 | $0 | $0 |
Recurring and Non-Recurring OM&R Costs | $746 | $1,668 | -$922 |
Capital Replacements | $446 | $0 | $446 |
Residual Value at End of Study Period | -$289 | -$481 | $193 |
------------ | ------------ | ------------ | |
Subtotal (for Future Cost Items) | $16,557 | $11,883 | $4,674 |
------------ | ------------ | ------------ | |
Total PV Life-Cycle Cost | $18,057 | $14,883 | $3,174 |
PV of Non-Investment Savings | $4,035 |
---|---|
- Increased Total Investment | $861 |
------------ | |
Net Savings | $3,174 |
SIR = | 4.69 |
AIRR = | 14.17% |
Simple Payback occurs in year | 5 |
---|---|
Discounted Payback occurs in year | 5 |
Energy | -----Average | Annual | Consumption----- | Life-Cycle |
---|---|---|---|---|
Type | Base Case | Alternative | Savings | Savings |
Electricity | 15,000.0 kWh | 10,250.0 kWh | 4,750.0 kWh | 71,240.2 kWh |
Energy | -----Average | Annual | Consumption----- | Life-Cycle |
---|---|---|---|---|
Type | Base Case | Alternative | Savings | Savings |
Electricity | 51.2 MBtu | 35.0 MBtu | 16.2 MBtu | 243.1 MBtu |
Energy | -----Average | Annual | Emissions----- | Life-Cycle |
---|---|---|---|---|
Type | Base Case | Alternative | Reduction | Reduction |
Electricity | ||||
CO2 | 17,759.09 kg | 12,135.38 kg | 5,623.71 kg | 84,344.13 kg |
SO2 | 58.87 kg | 40.23 kg | 18.64 kg | 279.58 kg |
NOx | 26.57 kg | 18.16 kg | 8.41 kg | 126.20 kg |
Total: | ||||
CO2 | 17,759.09 kg | 12,135.38 kg | 5,623.71 kg | 84,344.13 kg |
SO2 | 58.87 kg | 40.23 kg | 18.64 kg | 279.58 kg |
NOx | 26.57 kg | 18.16 kg | 8.41 kg | 126.20 kg |